5/27/2025
While commencement of the projects is still some time away, I thought, you may be interested is some fun facts about the project.
- We’ll be installing about 23 miles of pipe as part of the project, about the same distance from Mad River to Collinwood and back!
- There will be about 47 miles of wire installed, almost Collingwood to Barrie and back.
- The system will have about 1,454 sprinkler heads
If you have any other questions, you can reach me by email at
[email protected] or by phone at 705-428-3673.
Thank you,
Gary Ward,
General Manager/COO