9/30/2025
They will complete the final sand and sod installation during the 3
rd week of the month, remediation over the last week of the month and perhaps into the first week of November at which point their work is complete and they demobilize from the site.
The irrigation team will move to the front nine this week, starting on #4 and #7. An important aspect of the irrigation installation is moving to where we can keep our old system running and ensuring we have irrigation where the new sod is being laid.
I will continue to keep you informed through a couple of videos over the closing weeks of the season. Daily updates will also be posted on the Project Information Board and weekly updates in the Mad Post. I will also keep you informed of our performance against the budget.
Please continue to monitor the Project Information Board for the most up-to-date information.
If you have any other questions, you can reach me by email at
[email protected] or by phone at 705-428-3673.
Thank you,
Gary Ward,
General Manager/COO