Once the irrigation to #12, #17 and #6 green sites is up and running, Atkinson Irrigation will begin the hole-by-hole sprinkler installation. They will begin work at the far west end of the property (#17 and #16) and work their way through the back nine during the rest of August and September.

If Northgate Farms deliver to the schedule, they will complete all the bunker work in November, demobilize and exit the property. Atkinson will also work until the weather restricts the proper curing of the glue for the pipe and they will return to complete the project next spring.

I’ll provide a detailed financial update in next week’s article. The invoices for the sprinkler heads, pipe, associated parts and supplies have already been received and paid for and are right on the budget of $1.4M.

Both Doug Carrick and Sean Lavin, our project consultants, continue to visit and inspect on a weekly basis and will continue to do so. At this point, both are pleased with the quality of the work, and both continue to provide feedback and direction to the contractors and to the Club.

Please continue to monitor the Project Information Board for the most up-to-date information and I will continue to share daily videos during the week.

If you have any other questions, you can reach me by email at [email protected] or by phone at 705-428-3673.

Thank you,

Gary Ward,
General Manager/COO