7/22/2025

The Atkinson irrigation team continue to make excellent progress on the mainline installation. This week they will complete mainline work on #17 and will move over to install mainlines to #14, and #13. Next week they will complete mainline installation on #10 and #11 which will complete the back nine before moving over to the front nine.

Our irrigation consultant Sean Lavin is also on site every week to review work quality and prepare final course marking for the upcoming week.

I’ll provide updates on the financial status of the project at the end of July and while it’s still early, both contractors are slightly ahead of the work schedules.

Please continue to visit the Project Information Board on Member Central for the most up to date news on the day-to-day activities of both contractors.

Chad and I will continue to post videos to keep you visually informed.

If you have any other questions, you can reach me by email at [email protected] or by phone at 705-428-3673.

Thank you,

Gary Ward,
General Manager/COO